Manufacturing Global Manufacturing Corporation

SAP S/4HANA Implementation for Manufacturing Giant

Led the end-to-end SAP S/4HANA migration for a global manufacturing company with 12 plants across 3 time zones.

SAP
12
Team Members
18 months
Duration
5
Technologies
4
Key Outcomes

The Challenge

The client, a $2B global manufacturing company operating 12 plants across the US, Mexico, and Canada, was running SAP ECC 6.0 with heavily customized modules that had accumulated over a decade of technical debt. Their finance team took 15+ days for quarterly close, inventory accuracy hovered at 72%, and they had no real-time visibility into cross-plant operations.

SAP's announced end-of-mainstream-maintenance for ECC created urgency. Previous attempts with two Big 4 consulting firms had stalled due to scope creep and cost overruns. The client needed a partner who could deliver a brownfield migration within 18 months at a predictable cost.

Our Approach

We deployed a 12-member dedicated pod from our India delivery center — 4 SAP FICO consultants, 3 MM/SD functional leads, 2 Basis/HANA administrators, 2 Fiori UX developers, and 1 program manager. The team worked with 6 hours of daily EST overlap.

Our approach centered on SAP's Fit-to-Standard methodology to reduce custom code by 60%. We conducted a Custom Code Migration analysis using SAP's tools, identifying 4,200 custom objects — of which only 1,100 required migration. The remaining were replaced with standard S/4HANA functionality.

We implemented a "factory-by-factory" rollout strategy, starting with the smallest plant as a pilot, then replicating across all 12 locations. Each rollout followed a standardized 4-week playbook covering data migration, integration testing, user training, and cutover.

Project Timeline

1

Assessment & Planning

6 weeks

Custom code analysis, fit-to-standard workshops, migration roadmap, and plant prioritization

2

Pilot Plant Migration

12 weeks

First plant brownfield migration, FICO/MM/SD configuration, integration testing, user training

3

Scaled Rollout (Plants 2-6)

20 weeks

Standardized 4-week playbook per plant, parallel rollouts with dedicated cutover teams

4

Scaled Rollout (Plants 7-12)

20 weeks

Remaining plants with lessons-learned optimizations, Fiori dashboard deployment

5

Stabilization & Optimization

8 weeks

Hypercare support, performance tuning, analytics dashboard buildout, knowledge transfer

Key Outcomes

30% improvement in inventory accuracy
25% faster financial close cycles
50% cost savings vs. onshore
18 months to full rollout

The Results

The 18-month program was delivered on time and 15% under the original budget. Compared to the client's earlier Big 4 estimates, the total cost was 50% lower.

Financial close cycles dropped from 15 days to 4 days. Inventory accuracy improved from 72% to 97.5%. Real-time cross-plant dashboards enabled demand-driven production scheduling, reducing waste by 22%. The client's CFO presented the project as a case study at SAP Sapphire, highlighting the offshore delivery model as a key success factor.

"After two failed attempts with Big 4 firms, Offshore1st's SAP team delivered our S/4HANA migration on time and under budget. The quality of their functional consultants is outstanding — they challenged our assumptions and helped us simplify processes we'd been over-engineering for years."
M
Michael Torres
VP of IT, Global Manufacturing Corp

Tech Stack Used

SAP S/4HANA SAP MM SAP SD SAP FICO SAP Fiori